A BILL
To ensure efficiency and fairness in the awarding of
Federal contracts in connection with natural disaster reconstruction
efforts.
1.
Short
title
This Act may be cited as
the Local Disaster Contracting
Fairness Act of 2013.
2.
Definitions
In this Act:
(1)
Executive
agency
The term executive agency has the meaning
given such term in section 4 of the Office of Federal Procurement Policy Act
(41 U.S.C. 403).
(2)
Local
subcontractor
The term local subcontractor means,
with respect to a contract, a subcontractor who has a principal place of
business or regularly conducts operations in the area in which work is to be
performed under the contract by the subcontractor.
(3)
Natural
disaster reconstruction efforts
The term natural disaster
reconstruction efforts means reconstruction efforts undertaken in an
area subject to a declaration by the President of a major disaster under
section 401 of the Robert T. Stafford Disaster Relief and Emergency Assistance
Act (42 U.S.C. 5170).
3.
Federal
contracting requirements
(a)
In
general
The head of an
executive agency may not enter into an agreement for debris removal or
demolition services in connection with natural disaster reconstruction efforts
unless the agreement specifies that—
(1) all of the work
under the contract will be performed by the prime contractor or 1 or more
subcontractors at 1 tier under the contract;
(2) any work
performed under the contract by subcontractors will be performed by local
subcontractors, except to the extent that local subcontractors are not
available to perform such work;
(3) the prime
contractor will act as the project manager or construction manager for the
contract; and
(4) the prime
contractor—
(A) has primary
responsibility for managing all work under the contract; and
(B) will be paid a
certain percentage of the overall value of the contract as sole compensation
for assuming the risk associated with such responsibility.
(b)
Preference for
subcontractors affected by natural disasters
In entering into an
agreement for debris removal or demolition services in connection with natural
disaster reconstruction efforts, the head of an executive agency shall give a
preference in the source selection process to each offeror who certifies that
any work that is to be performed under the contract by subcontractors will be
performed by local subcontractors.
4.
Applicability
The requirements under section 3 shall apply
to agreements entered into on or after the date of the enactment of this