Library / Laws / 113th / s / S. 574 / Introduced in Senate
II
113th CONGRESS
1st Session
S. 574
IN THE SENATE OF THE UNITED STATES
March 14, 2013
Ms. Landrieu introduced
the following bill; which was read twice and referred to the
Committee on Environment and Public
Works
A BILL
To modify the project for navigation, Mississippi River
Ship Channel, Gulf of Mexico to Baton Rouge, Louisiana, and for other
purposes.
1.
Short title
This Act may be cited as the
Dredging for Restoration and
Economic Development for Global Exports Act of
2013 or the DREDGE Act of 2013.
2.
Mississippi River
Ship Channel, Gulf of Mexico to Baton Rouge, Louisiana
(a)
Project
modification
The project for
navigation, Mississippi River Ship Channel, Gulf of Mexico to Baton Rouge,
Louisiana, authorized by the matter under the heading Mississippi River Ship
Channel, Gulf to Baton Rouge, Louisiana of section
201(a) of the Water Resources Development Act of 1986 (100 Stat. 4090), is
modified as follows to direct the Secretary of the Army, acting through the
Chief of Engineers—
(1) to achieve,
operate, and maintain a navigation channel of 50 feet with respect to the
portion of the project from Baton Rouge to the Southwest Pass sea buoy;
(2) to complete the
work required under paragraph (1) not later than the last day of the third
fiscal year beginning after the date of enactment of this Act (completing at
least 1/3 of that work in each of the first 2 fiscal years
beginning after the date of enactment of this Act); and
(3) to conduct a pilot
disposal and sediment project in the Southwest Pass area to determine the
cost-effectiveness of pump-out disposal operations for hopper dredges
for—
(A) environmental
enhancement; and
(B) dredged material
disposal.
(b)
Consultation
In
carrying out subsection (a)(3), the Secretary of the Army, acting through the
Chief of Engineers, shall consult with appropriate Federal, State, and local
agencies and stakeholders to determine the safe placement and timing of
pump-out disposal operations that protect, create, restore, and nourish coastal
wetlands and aquatic habitat.
(c)
Treatment of
costs
All costs of the work required under subsection (a) shall
be treated as operation and maintenance costs, including the first costs of
achieving a navigation channel of 50 feet.
(d)
Federal
share
Notwithstanding section
101(b)(1) of the Water Resources Development Act of 1986 (33 U.S.C.
2211(b)(1)), the Federal share of the cost of the work required under
subsection (a) shall be 100 percent.
(e)
Funding
Notwithstanding
section 210 of the Water Resources Development Act of 1986 (33 U.S.C. 2238) or
section 9505 of the Internal Revenue Code of 1986, the Secretary of the Army,
acting through the Chief of Engineers, shall pay 100 percent of the costs of
the work required under subsection (a) out of amounts made available to the
Secretary from the Harbor Maintenance Trust Fund for operation and maintenance
expenses.
(f)
Report to
Congress
Not later than 2
years after the date of enactment of this Act, the Secretary of the Army,
acting through the Chief of Engineers, shall submit to Congress a report
on—
(1) the cost and the
environmental, storm damage reduction, and social benefits of the pump-out
disposal operation carried out under subsection (a)(3), as compared to standard
dredging practices for the area; and
(2) the total quantity
of dredge material produced during operation and maintenance activities in the
New Orleans District and the quantity that is beneficially used.
(g)
Limitation on
statutory construction
Nothing in this section affects the
authority of the Secretary of the Army with respect to the width of the project
referred to in subsection (a).