Library / Laws / 113th / s / S. 1397 / Introduced in Senate
II
113th CONGRESS
1st Session
S. 1397
IN THE SENATE OF THE UNITED STATES
July 30, 2013
Mr. Portman (for
himself, Mrs. McCaskill,
Mr. Donnelly, Mr. Enzi, and Mr.
Barrasso) introduced the following bill; which was read twice and
referred to the Committee on Homeland
Security and Governmental Affairs
A BILL
To improve the efficiency, management, and interagency
coordination of the Federal permitting process through reforms overseen by the
Director of the Office of Management and Budget, and for other
purposes.
1.
Short
title
This Act may be cited as
the Federal Permitting Improvement Act
of 2013.
2.
Definitions
In this Act:
(1)
Agency
The
term agency has the meaning given the term in section 551 of title
5, United States Code.
(2)
Agency
CPO
The term agency CPO means the chief permitting
officer of an agency designated by the head of the agency under section
3(b)(2)(A)(i).
(3)
Authorization
The
term authorization means—
(A) any license,
permit, approval, or other administrative decision required or authorized to be
issued by an agency with respect to the siting, construction, reconstruction,
or commencement of operations of a covered project under Federal law, whether
administered by a Federal or State agency; or
(B) any determination
or finding required to be issued by an agency—
(i) as
a precondition to an authorization described under paragraph (A); or
(ii) before an
applicant may take a particular action with respect to the siting,
construction, reconstruction, or commencement of operations of a covered
project under Federal law, whether administered by a Federal or State
agency.
(4)
Council
The
term Council means the Federal Infrastructure Permitting
Improvement Council established by section 3(a).
(5)
Covered
project
(A)
In
general
The term covered project means any
construction activity in the United States that requires authorization or
review by a Federal agency—
(i) involving
renewable or conventional energy production, electricity transmission, surface
transportation, aviation, ports and waterways, water resource projects,
broadband, pipelines, manufacturing, or any other sector as determined by the
Federal CPO; and
(ii) that is likely
to require an initial investment of more than $25,000,000, as determined by the
Federal CPO.
(B)
Exclusion
The
term covered project does not include any project subject to
section 101(b)(4) of title 23, United States Code.
(6)
Dashboard
The
term Dashboard means the Permitting Dashboard required by section
4(b).
(7)
Environmental
assessment
The term environmental assessment means a
concise public document for which a Federal agency is responsible that
serves—
(A) to briefly
provide sufficient evidence and analysis for determining whether to prepare an
environmental impact statement or a finding of no significant impact;
(B) to aid in the
compliance of the agency with NEPA if an environmental impact statement is not
necessary; and
(C) to facilitate
preparation of an environmental impact statement, if an environmental impact
statement is necessary.
(8)
Environmental
document
The term environmental document means an
environmental assessment or environmental impact statement.
(9)
Environmental
impact statement
The term environmental impact
statement means the detailed statement of significant environmental
impacts required to be prepared under NEPA.
(10)
Environmental
review
The term environmental review means the
agency procedures for preparing an environmental impact statement,
environmental assessment, categorical exclusion, or other document required
under NEPA.
(11)
Federal
CPO
The term Federal CPO means the Federal Chief
Permitting Officer appointed by the President under section 3(b)(1).
(12)
Inventory
The
term inventory means the inventory of covered projects established
by the Federal CPO under section 3(c)(1)(A).
(13)
Lead
agency
The term lead agency means the agency with
principal responsibility for review and authorization of a covered project, as
determined under section 3(c)(1)(B).
(14)
NEPA
The
term NEPA means the National Environmental Policy Act of 1969 (42
U.S.C. 4321 et seq.).
(15)
Participating
agency
The term participating agency means any
agency participating in reviews or authorizations for a particular covered
project in accordance with section 4.
(16)
Project
sponsor
The term project sponsor means the entity,
including any private, public, or public-private entity, that seeks approval
for a project.
3.
Federal
Permitting Improvement Council
(a)
Establishment
There
is established the Federal Permitting Improvement Council.
(b)
Composition
(1)
Chair
The
President shall appoint an officer of the Office of Management and Budget as
the Federal Chief Permitting Officer to serve as Chair of the Council, by and
with the advice and consent of the Senate.
(2)
Chief
Permitting Officers
(A)
In
general
(i)
Designation by
head of agency
Each individual listed in subparagraph (B) shall
designate a member of the agency in which the individual serves to serve as the
agency CPO.
(ii)
Qualifications
The
agency CPO described in clause (i) shall hold a position in the agency of the
equivalent of a deputy secretary or higher.
(iii)
Membership
Each
agency CPO described in clause (i) shall serve on the Council.
(B)
Heads of
agencies
The individuals that shall each designate an agency CPO
under this subparagraph are as follows:
(i) The
Secretary of Agriculture.
(ii) The Secretary of
Commerce.
(iii) The Secretary
of the Interior.
(iv) The Secretary of
Energy.
(v) The
Secretary of Transportation.
(vi) The Secretary of
Defense.
(vii) The
Administrator of the Environmental Protection Agency.
(viii) The Chairman
of the Federal Energy Regulatory Commission.
(ix) The Chairman of
the Nuclear Regulatory Commission.
(x) The
Chairman of the Advisory Council on Historic Preservation.
(xi) Any other head
of a Federal agency that the Federal CPO may invite to participate as a member
of the Council.
(3)
Chairman of the
Council on Environmental Quality
In addition to the members
listed in paragraphs (1) and (2), the Chairman of the Council on Environmental
Quality shall also be a member of the Council.
(c)
Duties
(1)
Federal
CPO
(A)
Inventory
development
The Federal CPO, in consultation with the members of
the Council, shall—
(i) not
later than 3 months after the date of enactment of this Act, establish an
inventory of covered projects that are pending the review or authorization of
the head of any Federal agency;
(ii)
(I) categorize the projects
in the inventory as appropriate based on the project type; and
(II) for each category, identify the types of
reviews and authorizations most commonly involved; and
(iii) add covered
projects to the inventory after the Federal CPO receives a notice described in
section 4(a)(1).
(B)
Lead agency
designation
The Federal CPO, in consultation with the Council,
shall—
(i) designate a lead
agency for each category of covered projects described in subparagraph (A)(ii);
and
(ii) publish on an
Internet website the designations and categories in an easily accessible
format.
(C)
Performance
schedules
(i)
In
general
The Federal CPO, in consultation with the Council, shall
develop nonbinding performance schedules, including intermediate and final
deadlines, for reviews and authorizations for each category of covered projects
described in subparagraph (A)(ii).
(ii)
Requirements
(I)
In
general
The performance schedules shall reflect employment of the
use of the most efficient applicable processes.
(II)
Limit
The
final deadline for completion of any review or authorization contained in the
performance schedules shall not be later than 180 days after the date on which
the completed application or request is filed.
(iii)
Review and
revision
Not later than 2 years after the date on which the
performance schedules are established under this subparagraph, and not less
frequently than once every 2 years thereafter, the Federal CPO, in consultation
with the Council, shall review and revise the performance schedules.
(D)
Guidance
The
Federal CPO may issue circulars, bulletins, guidelines, and other similar
directives as necessary to carry out responsibilities under this Act and to
effectuate the adoption by agencies of the best practices and recommendations
of the Council described in paragraph (2).
(2)
Council
(A)
Recommendations
(i)
In
general
The Council shall make recommendations to the Federal CPO
with respect to the designations under paragraph (1)(B) and the performance
schedules under paragraph (1)(C).
(ii)
Update
The
Council may update the recommendations described in clause (i).
(B)
Best
practices
Not later than 1 year after the date of enactment of
this Act, and at least annually thereafter, the Council shall issue
recommendations on the best practices for—
(i) early stakeholder
engagement, including fully considering and, as appropriate, incorporating
recommendations provided in public comments on any proposed covered
project;
(ii) assuring
timeliness of permitting and review decisions;
(iii) coordination
between Federal and non-Federal governmental entities;
(iv) transparency;
(v) reduction of
information collection requirements and other administrative burdens on
agencies, project sponsors, and other interested parties;
(vi) evaluating lead
agencies and participating agencies under this Act; and
(vii) other aspects
of infrastructure permitting, as determined by the Council.
4.
Permitting
process improvement
(a)
Project
initiation and designation of participating agencies
(1)
Notice
(A)
In
general
A project sponsor shall provide the Federal CPO and the
lead agency notice of the initiation of a proposed covered project.
(B)
Contents
Each
notice described in subparagraph (A) shall include—
(i) a
description, including the general location, of the proposed project;
(ii) a
statement of any Federal authorization or review anticipated to be required for
the proposed project; and
(iii) an assessment
of the reasons why the proposed project meets the definition of a covered
project in section 2.
(2)
Invitation
(A)
In
general
Not later than 45 days after the date on which a lead
agency receives the notice under paragraph (1), the lead agency shall—
(i) identify another
agency that may have an interest in the proposed project; and
(ii) invite the
agency to become a participating agency in the permitting management process
and in the environmental review process described in section 6.
(B)
Deadlines
Each
invitation made under subparagraph (A) shall include a deadline for a response
to be submitted to the lead agency.
(3)
Participating
agencies
An agency invited under paragraph (2) shall be
designated as a participating agency for a covered project, unless the agency
informs the lead agency in writing before the deadline described in paragraph
(2)(B) that the agency—
(A) has no
jurisdiction or authority with respect to the proposed project; or
(B) does not intend
to exercise authority related to, or submit comments on, the proposed
project.
(4)
Effect of
designation
The designation described in paragraph (3) shall not
give the participating agency jurisdiction over the proposed project.
(5)
Change of lead
agency
(A)
In
general
On the request of a lead agency, participating agency, or
project sponsor, the Federal CPO may designate a different agency as the lead
agency for a covered project if the Federal CPO receives new information
regarding the scope or nature of a covered project that indicates that the
project should be placed in a different category under section
3(c)(1)(B).
(B)
Resolution of
dispute
Any dispute over designation of a lead agency for a
particular covered project shall be resolved by the Federal CPO.
(b)
Permitting
Dashboard
(1)
Requirement to
maintain
(A)
In
general
The Federal CPO, in coordination with the Administrator
of General Services, shall maintain an online database to be known as the
Permitting Dashboard to track the status of Federal reviews and
authorizations for any covered project in the inventory.
(B)
Specific and
searchable entry
The Dashboard shall include a specific and
searchable entry for each project.
(2)
Additions
Not
later than 7 days after the date on which the Federal CPO receives a notice
under subsection (a)(1), the Federal CPO shall create a specific entry on the
Dashboard for the project, unless the Federal CPO or lead agency determines
that the project is not a covered project.
(3)
Submissions by
agencies
The lead agency and each participating agency shall
submit to the Federal CPO for posting on the Dashboard for each covered
project—
(A) any application
and any supporting document submitted by a project sponsor for any required
Federal review or authorization for the project;
(B) not later than 2
business days after the date on which any agency action or decision that
materially affects the status of the project is made, a description, including
significant supporting documents, of the agency action or decision; and
(C) the status of any
litigation to which the agency is a party that is directly related to the
project, including, if practicable, any judicial document made available on an
electronic docket maintained by a Federal, State, or local court.
(4)
Postings by the
Federal CPO
The Federal CPO shall post on the Dashboard an entry
for each covered project that includes—
(A) the information
submitted under paragraph (3)(A) not later than 2 days after the date on which
the Federal CPO receives the information;
(B) a permitting
timetable approved by the Federal CPO under subsection (c)(2)(C);
(C) the status of the
compliance of each participating agency with the permitting timetable;
(D) any modifications
of the permitting timetable; and
(E) an explanation of
each modification described in subparagraph (D).
(c)
Coordination
and timetables
(1)
Coordination
plan
(A)
In
general
Not later than 60 days after the date on which the lead
agency receives a notice under subsection (a)(1), the lead agency, in
consultation with each participating agency, shall establish a concise plan for
coordinating public and agency participation in, and completion of, any
required Federal review and authorization for the project.
(B)
Memorandum of
understanding
The lead agency may incorporate the coordination
plan described in subparagraph (A) into a memorandum of understanding.
(2)
Permitting
timetable
(A)
Establishment
As
part of the coordination plan required by paragraph (1), the lead agency, in
consultation with each participating agency, the project sponsor, and the State
in which the project is located, shall establish a permitting timetable that
includes intermediate and final deadlines for action by each participating
agency on any Federal review or authorization required for the project.
(B)
Factors for
consideration
In establishing the permitting timetable under
subparagraph (A), the lead agency shall follow the performance schedules
established under section 3(c)(1)(C), but may vary the timetable based on
relevant factors, including—
(i) the
size and complexity of the covered project;
(ii) the resources
available to each participating agency;
(iii) the regional or
national economic significance of the project;
(iv) the sensitivity
of the natural or historic resources that may be affected by the project;
and
(v) the
extent to which similar projects in geographic proximity to the project were
recently subject to environmental review or similar procedures under State
law.
(C)
Approval by the
Federal CPO
(i)
Requirement to
submit
The lead agency shall promptly submit to the Federal CPO a
permitting timetable established under subparagraph (A) for review.
(ii)
Revision and
approval
(I)
In
general
The Federal CPO, after consultation with the lead agency,
may revise the permitting timetable if the Federal CPO determines that the
timetable deviates without reasonable justification from the performance
schedule established under section 3(c)(1)(C).
(II)
No revision by
Federal CPO within 7 days
If the Federal CPO does not revise the
permitting timetable earlier than the date that is 7 days after the date on
which the lead agency submits to the Federal CPO the permitting timetable, the
permitting timetable shall be approved by the Federal CPO.
(D)
Modification
after approval
The lead agency may modify a permitting timetable
established under subparagraph (A) for good cause only if—
(i) the
lead agency and the affected participating agency agree to a different
deadline;
(ii) the lead agency
or the affected participating agency provides a written explanation of the
justification for the modification; and
(iii) the lead agency
submits to the Federal CPO a modification, which the Federal CPO may revise or
disapprove.
(E)
Consistency
with other time periods
A permitting timetable established under
subparagraph (A) shall be consistent with any other relevant time periods
established under Federal law.
(F)
Compliance
(i)
In
general
Each Federal participating agency shall comply with the
deadlines set forth in the permitting timetable approved under subparagraph
(C), or with any deadline modified under subparagraph (D).
(ii)
Failure to
comply
If a Federal participating agency fails to comply with a
deadline for agency action on a covered project, the head of the participating
agency shall—
(I) promptly report
to the Federal CPO for posting on the Dashboard an explanation of any specific
reason for failing to meet the deadline and a proposal for an alternative
deadline; and
(II) report to the
Federal CPO for posting on the Dashboard a monthly status report describing any
agency activity related to the project until the agency has taken final action
on the delayed authorization or review.
(3)
Cooperating
State, local, or tribal governments
(A)
In
general
To the maximum extent practicable under applicable
Federal law, the lead agency shall coordinate the Federal review and
authorization process under this subsection with any State, local, or tribal
agency responsible for conducting any separate review or authorization of the
covered project to ensure timely and efficient review and permitting
decisions.
(B)
Memorandum of
understanding
(i)
In
general
Any coordination plan between the lead agency and any
State, local, or tribal agency shall, to the maximum extent practicable, be
included in a memorandum of understanding.
(ii)
Submission to
Federal CPO
A lead agency shall submit to the Federal CPO each
memorandum of understanding described in clause (i).
(iii)
Post to
Dashboard
The Federal CPO shall post to the Dashboard each
memorandum of understanding submitted under clause (ii).
(d)
Early
consultation
The lead agency shall provide an expeditious process
for project sponsors to confer with each participating agency involved and to
have each participating agency determine and communicate to the project
sponsor, not later than 60 days after the date on which the project sponsor
submits a request, information concerning—
(1) the likelihood of
approval for a potential covered project; and
(2) key issues of
concern to each participating agency and to the public.
(e)
Cooperating
agency
(1)
In
general
A lead agency may designate a participating agency as a
cooperating agency in accordance with part 1501 of title 40, Code of Federal
Regulations (or successor regulations).
(2)
Effect on other
designation
The designation described in paragraph (1) shall not
affect any designation under subsection (a)(3).
(3)
Limitation on
designation
Any agency not designated as a participating agency
under subsection (a)(3) shall not be designated as a cooperating agency under
paragraph (1).
5.
Interstate
compacts
The consent of
Congress is given for 3 or more contiguous States to enter into an interstate
compact establishing regional infrastructure development agencies to facilitate
authorization and review of covered projects, under State law or in the
exercise of delegated permitting authority described under section 7, that will
advance infrastructure development, production, and generation within the
States that are parties to the compact.
6.
Coordination of
required reviews
(a)
Concurrent
reviews
Each agency shall, to the greatest extent permitted by
law—
(1) carry out the
obligations of the agency under other applicable law concurrently, and in
conjunction with other reviews being conducted by other participating agencies,
including environmental reviews required under NEPA, unless doing so would
impair the ability of the agency to carry out statutory obligations; and
(2) formulate and
implement administrative, policy, and procedural mechanisms to enable the
agency to ensure completion of the environmental review process in a timely,
coordinated, and environmentally responsible manner.
(b)
Adoption and
use of documents
(1)
State
environmental documents; supplemental documents
(A)
Use of existing
documents
On the request of a project sponsor, a lead agency
shall consider and, as appropriate, adopt or incorporate, a document that has
been prepared for a project under State laws and procedures as the
environmental impact statement or environmental assessment for the project if
the State laws and procedures under which the document was prepared provide, as
determined by the lead agency in consultation with the Council on Environmental
Quality, environmental protection and opportunities for public participation
that are substantially equivalent to NEPA.
(B)
NEPA
obligations
An environmental document adopted under subparagraph
(A) may serve as, or supplement, an environmental impact statement or
environmental assessment required to be prepared by a lead agency under
NEPA.
(C)
Supplemental
document
In the case of an environmental document described in
subparagraph (A), during the period after preparation of the document and prior
to the adoption of the document by the lead agency, the lead agency shall
prepare and publish a supplemental document to the document if the lead agency
determines that—
(i) a
significant change has been made to the project that is relevant for purposes
of environmental review of the project; or
(ii) there have been
significant changes in circumstances or availability of information relevant to
the environmental review for the project.
(D)
Comments
If
a lead agency prepares and publishes a supplemental document under subparagraph
(C), the lead agency may solicit comments from other agencies and the public on
the supplemental document for a period of not more than 30 days beginning on
the date on which the supplemental document is published.
(E)
Record of
decision
A lead agency shall issue a record of decision or
finding of no significant impact, as appropriate, based on the document adopted
under subparagraph (A) and any supplemental document prepared under
subparagraph (C).
(c)
Alternatives
analysis
(1)
Participation
As
early as practicable during the environmental review, but not later than the
commencement of scoping for a project requiring the preparation of an
environmental impact statement, the lead agency shall provide an opportunity
for the involvement of cooperating agencies in determining the range of
alternatives to be considered for a project.
(2)
Range of
alternatives
Following participation under paragraph (1), the
lead agency shall determine the range of alternatives for consideration in any
document that the lead agency is responsible for preparing for the
project.
(3)
Methodologies
The
lead agency shall determine, in collaboration with each cooperating agency at
appropriate times during the environmental review, the methodologies to be used
and the level of detail required in the analysis of each alternative for a
project.
(4)
Preferred
alternative
At the discretion of the lead agency, the preferred
alternative for a project, after being identified, may be developed to a higher
level of detail than other alternatives to facilitate the development of
mitigation measures or concurrent compliance with other applicable laws if the
lead agency determines that the development of the higher level of detail will
not prevent—
(A) the lead agency
from making an impartial decision as to whether to accept another alternative
that is being considered in the environmental review; and
(B) the public from
commenting on the preferred and other alternatives
(d)
Environmental
review comments
(1)
Comments on
draft environmental impact statement
For comments by an agency or
the public on a draft environmental impact statement, the lead agency shall
establish a comment period of not more than 60 days after the date on which a
notice announcing availability of the environmental impact statement is
published in the Federal Register, unless—
(A) the lead agency,
the project sponsor, and each participating agency agree to a different
deadline; or
(B) the deadline is
extended by the lead agency for good cause.
(2)
Other
comments
For all other comment periods for agency or public
comments in the environmental review process, the lead agency shall establish a
comment period of not later than 30 days after the date on which the materials
on which comment is requested are made available, unless—
(A) the lead agency,
the project sponsor, and each participating agency agree to a different
deadline; or
(B) the lead agency
modifies the deadline for good cause.
(e)
Issue
identification and resolution
(1)
Cooperation
The
lead agency and each participating agency shall work cooperatively in
accordance with this section to identify and resolve issues that could delay
completion of the environmental review or could result in denial of any
approval required for the project under applicable laws.
(2)
Lead agency
responsibilities
(A)
In
general
The lead agency shall make information available to each
participating agency as early as practicable in the environmental review
regarding the environmental, historic, and socioeconomic resources located
within the project area and the general locations of the alternatives under
consideration.
(B)
Sources of
information
The information described in subparagraph (A) may be
based on existing data sources, including geographic information systems
mapping.
(3)
Participating
agency responsibilities
Based on information received from the
lead agency under paragraph (2), each participating agency shall identify, as
early as practicable, any issues of concern, including any issues that could
substantially delay or prevent an agency from granting a permit or other
approval needed for the project, regarding any potential environmental,
historic, or socioeconomic impacts of the project.
(f)
Categories of
projects
The authorities granted under this section may be
exercised for an individual project or a category of projects.
7.
Delegated State
permitting programs
If a
Federal statute permits a State to be delegated or otherwise authorized by a
Federal agency to issue or otherwise administer a permit program in lieu of the
Federal agency, each member of the Council shall—
(1) on publication by
the Council of best practices under section 3(c)(2)(B), initiate a process,
with public participation, to determine whether and the extent to which any of
the best practices are applicable to permitting under the statute; and
(2) not later than 2
years after the date of enactment of this Act, make recommendations for State
modifications of the permit program to reflect the best practices described in
section (3)(c)(2)(B), as appropriate.
8.
Litigation,
judicial review, and savings provision
(a)
Limitations on
claims
(1)
In
general
Notwithstanding any other provision of law, a claim
arising under Federal law seeking judicial review of any authorization issued
by a Federal agency for a covered project shall be barred unless—
(A) the action is
filed not later than 150 days after the date on which a notice is published in
the Federal Register that the authorization is final pursuant to the law under
which the agency action is taken, unless a shorter time is specified in the
Federal law under which judicial review is allowed; and
(B) in the case of an
action pertaining to an environmental review conducted under NEPA—
(i) the
action is filed by a party that submitted a comment during the environmental
review on the issue on which the party seeks judicial review; and
(ii) the comment was
sufficiently detailed to put the lead agency on notice of the issue on which
the party seeks judicial review.
(2)
New
information
(A)
In
general
The head of a lead agency or participating agency shall
consider new information received after the close of a comment period if the
information satisfies the requirements under regulations implementing
NEPA.
(B)
Supplemental
environmental impact statement
If the preparation of a
supplemental environmental impact statement is required, the preparation of the
supplemental environmental impact statement shall be considered a separate
final agency action and the deadline for filing a claim for judicial review of
the agency action shall be 150 days after the date on which a notice announcing
the agency action is published in the Federal Register.
(3)
Rule of
construction
Nothing in this subsection creates a right to
judicial review or places any limit on filing a claim that a person has
violated the terms of an authorization.
(b)
Preliminary
injunctive relief
In addition to considering any other applicable
equitable factors, including the effects on public health, safety, and the
environment, in any action seeking a temporary restraining order or preliminary
injunction against an agency or a project sponsor in connection with review or
authorization of a covered project, the court shall—
(1) consider the
potential for significant job losses or other economic harm resulting from an
order or injunction; and
(2) not presume that
the harms described in paragraph (1) are reparable.
(c)
Judicial
review
Except as provided in subsection (a), nothing in this Act
affects the reviewability of any final Federal agency action in a court of the
United States or in the court of any State.
(d)
Savings
clause
Nothing in this Act—
(1) supersedes,
amends, or modifies NEPA or any other Federal environmental statute or affects
the responsibility of any Federal officer to comply with or enforce any
statute; or
(2) creates a
presumption that a covered project will be approved or favorably reviewed by
any agency.
(e)
Limitations
Nothing
in this section preempts, limits, or interferes with—
(1) any practice of
seeking, considering, or responding to public comment; or
(2) any power,
jurisdiction, responsibility, or authority that a Federal, State, or local
governmental agency, metropolitan planning organization, Indian tribe, or
project sponsor has with respect to carrying out a project or any other
provisions of law applicable to any project, plan, or program.
9.
Report to
Congress
(a)
In
general
Not later than April
15 of each year, the Federal CPO shall submit to Congress a report detailing
the progress accomplished under this Act during the previous fiscal
year.
(b)
Contents
The report described in subsection (a)
shall assess the performance of each participating agency and lead agency based
on the best practices described in section 3(c)(2)(B).
(c)
Opportunity To
include comments
Each agency
CPO shall have the opportunity to include comments concerning the performance
of the agency in the report described in subsection (a).
10.
Application
This Act applies to any covered project for
which an application or request for a Federal authorization is pending before a
Federal agency 90 days after the date of enactment of this Act.