Library / Laws / 113th / hr / H.R. 761 / Introduced in House
I
113th CONGRESS
1st Session
H. R. 761
IN THE HOUSE OF REPRESENTATIVES
February 15, 2013
Mr. Amodei (for
himself, Mr. Gosar,
Mr. Lamborn,
Mr. Bishop of Utah,
Mr. Jones,
Mr. Walberg,
Mr. Franks of Arizona,
Mr. Heck of Nevada,
Mr. Tipton,
Mr. Walden,
Mr. Stivers,
Mr. Johnson of Ohio,
Mr. Latta,
Mr. Young of Alaska,
Mr. Conaway,
Mr. Benishek,
Mr. Daines,
Mr. Gardner,
Mr. Schweikert,
Mr. Matheson,
Mr. Bishop of Georgia,
Mr. Labrador,
Mr. Stewart,
Mr. Chaffetz,
Mr. Salmon,
Mr. Simpson,
Mr. Gohmert,
Mr. Pearce, and
Mr. Luetkemeyer) introduced the
following bill; which was referred to the Committee on Natural Resources, and in
addition to the Committee on the Judiciary, for a period to be
subsequently determined by the Speaker, in each case for consideration of such
provisions as fall within the jurisdiction of the committee
concerned
A BILL
To require the Secretary of the Interior and the
Secretary of Agriculture to more efficiently develop domestic sources of the
minerals and mineral materials of strategic and critical importance to United
States economic and national security and manufacturing
competitiveness.
1.
Short title
This Act may be cited as the
National Strategic and Critical
Minerals Production Act of 2013.
2.
Findings
Congress finds the following:
(1) The
industrialization of China and India has driven demand for nonfuel mineral
commodities, sparking a period of resource nationalism exemplified by China’s
reduction in exports of rare-earth elements necessary for telecommunications,
military technologies, healthcare technologies, and conventional and renewable
energy technologies.
(2) The availability
of minerals and mineral materials are essential for economic growth, national
security, technological innovation, and the manufacturing and agricultural
supply chain.
(3) The exploration,
production, processing, use, and recycling of minerals contribute significantly
to the economic well-being, security and general welfare of the Nation.
(4) The United States
has vast mineral resources, but is becoming increasingly dependent upon foreign
sources of these mineral materials, as demonstrated by the following:
(A) Twenty-five years
ago the United States was dependent on foreign sources for 30 nonfuel mineral
materials, 6 of which the United States imported 100 percent of the Nation’s
requirements, and for another 16 commodities the United States imported more
than 60 percent of the Nation’s needs.
(B) By 2011 the United
States import dependence for nonfuel mineral materials had more than doubled
from 30 to 67 commodities, 19 of which the United States imported 100 percent
of the Nation’s requirements, and for another 24 commodities, imported more
than 50 percent of the Nation’s needs.
(C) The United States
share of worldwide mineral exploration dollars was 8 percent in 2011, down from
19 percent in the early 1990s.
(D) In the 2012 Ranking of Countries for Mining
Investment, out of 25 major mining countries, the United States ranked last
with Papua New Guinea in permitting delays, and towards the bottom regarding
government take and social issues affecting mining.
3.
Definitions
In this Act:
(1)
Strategic and
critical minerals
The term strategic and critical
minerals means minerals that are necessary—
(A) for national
defense and national security requirements;
(B) for the Nation’s
energy infrastructure, including pipelines, refining capacity, electrical power
generation and transmission, and renewable energy production;
(C) to support
domestic manufacturing, agriculture, housing, telecommunications, healthcare,
and transportation infrastructure; and
(D) for the Nation’s
economic security and balance of trade.
(2)
Agency
The
term agency means any agency, department, or other unit of
Federal, State, local, or tribal government, or Alaska Native
Corporation.
(3)
mineral
exploration or mine permit
The term mineral exploration or mine
permit includes plans of operation issued by the Bureau of Land
Management and the Forest Service pursuant to 43 C.F.R. 3809 and 36 C.F.R.
228A, respectively.
I
Development of
Domestic Sources of Strategic and Critical Minerals
101.
Improving
development of strategic and critical minerals
Domestic mines that will provide strategic
and critical minerals shall be considered an infrastructure
project as described in Presidential Order Improving Performance
of Federal Permitting and Review of Infrastructure Projects dated March
22, 2012.
102.
Responsibilities
of the lead agency
(a)
In
general
The lead agency with responsibility for issuing a mineral
exploration or mine permit shall appoint a project lead who shall coordinate
and consult with other agencies, cooperating agencies, project proponents and
contractors to ensure that agencies minimize delays, set and adhere to
timelines and schedules for completion of reviews, set clear permitting goals
and track progress against those goals.
(b)
Determination
under NEPA
The lead agency
with responsibility for issuing a mineral exploration or mine permit shall
determine any such action would not constitute a major Federal action
significantly affecting the quality of the human environment within the meaning
of the National Environmental Policy Act of 1969 if the procedural and
substantive safeguards of the lead agency’s permitting process alone, any
applicable State permitting process alone, or a combination of the two
processes together provide an adequate mechanism to ensure that environmental
factors are taken into account.
(c)
coordination on
permitting and review
The lead agency with responsibility for
issuing a mineral exploration or mine permit shall enhance government
coordination on permitting and review by avoiding duplicative reviews,
minimizing paperwork and engaging other agencies and stakeholders early in the
process. The lead agency shall consider the following best practices:
(1) Deferring to and
relying upon baseline data, analysis and reviews preformed by State agencies
with jurisdiction over the proposed project.
(2) Conducting reviews
concurrently rather than sequentially to the extent practicable and when such
concurrent review will expedite rather than delay a decision.
(d)
time limits for
permit review process
At the request of a project proponent, the
project lead of the agency with responsibility for issuing a mineral
exploration or mine permit shall enter into an agreement with the project
proponent and other cooperating agencies that sets time limits for each part of
the permit review process including the following:
(1) The decision on whether to prepare a
document required under the National Environmental Policy Act of 1969.
(2) A determination of the scope of any
document required under the National Environmental Policy Act of 1969.
(3) The scope of and
schedule for the baseline studies required to prepare a document required under
the National Environmental Policy Act of 1969.
(4) Preparation of any draft document required
under the National Environmental Policy Act of 1969.
(5) Preparation of a final document required
under the National Environmental Policy Act of 1969.
(6) Consultations
required under applicable laws.
(7) Submission and
review of any comments required under applicable law.
(8) Publication of any
public notices required under applicable law.
(9) A
final or any interim decisions.
(e)
Time limit for
total review process
In no case should the total review process
described in subsection (d) exceed 30 months unless agreed to by the
signatories of the agreement.
(f)
Limitation on
addressing public comments
The lead agency is not required to address
agency or public comments that were not submitted during the public comment
periods provided by the lead agency or otherwise required by law.
(g)
Financial
assurance
The lead agency
will determine the amount of financial assurance for reclamation of a mineral
exploration or mining site, which must cover the estimated cost if the lead
agency were to contract with a third party to reclaim the operations according
to the reclamation plan, including construction and maintenance costs for any
treatment facilities necessary to meet Federal, State or tribal environmental
standards.
(h)
Application to
existing permit applications
This section shall apply with respect to a
mineral exploration or mine permit for which an application was submitted
before the date of the enactment of this Act if the applicant for the permit
submits a written request to the lead agency for the permit. The lead agency
shall begin implementing this section with respect to such application within
30 days after receiving such written request.
(i)
Strategic and
critical materials within National Forests
With respect to strategic and critical
materials within a federally administered unit of the National Forest System,
the lead agency shall—
(1) exempt all areas of identified mineral
resources in Land Use Designations, other than Non-Development Land Use
Designations, in existence as of the date of the enactment of this Act from the
procedures detailed at and all rules promulgated under part 294 of title 36,
Code for Federal Regulations;
(2) apply such exemption to all additional
routes and areas that the lead agency finds necessary to facilitate the
construction, operation, maintenance, and restoration of the areas of
identified mineral resources described in paragraph (1); and
(3) continue to apply such exemptions after
approval of the Minerals Plan of Operations for the unit of the National Forest
System.
103.
Conservation of
the resource
In developing the
mineral exploration or mine permit, the priority of the lead agency shall be to
maximize the development of the mineral resource, while mitigating
environmental impacts, so that more of the mineral resource can be brought to
the market place.
104.
Federal
register process for mineral exploration and mining projects
(a)
Preparation of
Federal Notices for Mineral Exploration and Mine Development
Projects
The preparation of
Federal Register notices required by law associated with the issuance of a
mineral exploration or mine permit shall be delegated to the organization level
within the agency responsible for issuing the mineral exploration or mine
permit. All Federal Register notices regarding official document availability,
announcements of meetings, or notices of intent to undertake an action shall be
originated and transmitted to the Federal Register from the office where
documents are held, meetings are held, or the activity is initiated.
(b)
Departmental
Review of Federal Register Notices for Mineral Exploration and Mining
Projects
Absent any
extraordinary circumstance or except as otherwise required by any Act of
Congress, each Federal Register notice described in subsection (a) shall
undergo any required reviews within the Department of the Interior or the
Department of Agriculture and be published in its final form in the Federal
Register no later than 30 days after its initial preparation.
II
Judicial review
of agency actions relating to Exploration and Mine Permits
201.
Definitions for
title
In this title the term
covered civil action means a civil action against the Federal
Government containing a claim under section 702 of title 5, United States Code,
regarding agency action affecting a mineral exploration or mine permit.
202.
Timely
filings
A covered civil action
is barred unless filed no later than the end of the 60-day period beginning on
the date of the final Federal agency action to which it relates.
203.
Right to
intervene
The holder of any
mineral exploration or mine permit may intervene as of right in any covered
civil action by a person affecting rights or obligations of the permit holder
under the permit.
204.
Expedition in
hearing and determining the action
The court shall endeavor to hear and
determine any covered civil action as expeditiously as possible.
205.
Limitation on
prospective relief
In a
covered civil action, the court shall not grant or approve any prospective
relief unless the court finds that such relief is narrowly drawn, extends no
further than necessary to correct the violation of a legal requirement, and is
the least intrusive means necessary to correct that violation.
206.
Limitation on
attorneys’ fees
Sections 504
of title 5, United States Code, and 2412 of title 28, United States Code
(together commonly called the Equal Access to Justice Act) do not apply to a
covered civil action, nor shall any party in such a covered civil action
receive payment from the Federal Government for their attorneys’ fees,
expenses, and other court costs.