Library / Laws / 113th / hr / H.R. 697 / Reported in House
IB
Union Calendar No. 99
113th CONGRESS
1st Session
H. R. 697
[Report No.
113–137]
IN THE HOUSE OF
REPRESENTATIVES
February 14, 2013
Mr. Heck of Nevada
(for himself, Mr. Amodei,
Mr. Horsford, and
Ms. Titus) introduced the following
bill; which was referred to the
Committee on Natural
Resources
July 8, 2013
Reported with an amendment, committed to the Committee of
the Whole House on the State of the Union, and ordered to be
printed
Strike out all after the enacting clause and insert
the part printed in italic
For text of introduced bill, see copy of bill as
introduced on February 14, 2013
A BILL
To provide for the conveyance of certain
Federal land in Clark County, Nevada, for the environmental remediation and
reclamation of the Three Kids Mine Project Site, and for other
purposes.
1.
Short title
This Act may be cited as the
Three Kids Mine Remediation and
Reclamation Act.
2.
Definitions
In this Act:
(1)
Federal
land
The term Federal land means the approximately
948 acres of Bureau of Reclamation and Bureau of Land Management land within
the Three Kids Mine Project Site, as depicted on the map.
(2)
Hazardous substance;
pollutant or contaminant; remedy
The terms hazardous
substance, pollutant or contaminant, and
remedy have the meanings given those terms in section 101 of the
Comprehensive Environmental Response, Compensation, and Liability Act of 1980
(42 U.S.C. 9601).
(3)
Henderson Redevelopment
Agency
The term Henderson Redevelopment Agency means
the redevelopment agency of the City of Henderson, Nevada, established and
authorized to transact business and exercise the powers of the agency in
accordance with the Nevada Community Redevelopment Law (Nev. Rev. Stat. 279.382
to 279.685).
(4)
Map
The
term map means the map entitled Three Kids Mine Project
Area and dated February 6, 2012.
(5)
Responsible
Party
The term Responsible Party means the private
sector entity designated by the Henderson Redevelopment Agency, and approved by
the State of Nevada, to complete the assessment, remediation, reclamation and
redevelopment of the Three Kids Mine Project Site).
(6)
Secretary
The
term Secretary means the Secretary of the Interior.
(7)
State
The
term State means the State of Nevada.
(8)
Three Kids Mine Project
Site
The term Three Kids Mine Project Site means the
approximately 1,262 acres of land that is—
(A) comprised of—
(i) the Federal land;
and
(ii) the approximately 314
acres of adjacent non-Federal land; and
(B) depicted as the
Three Kids Mine Project Site on the map.
3.
Land conveyance
(a)
In
general
Notwithstanding sections 202 and 203 of the Federal Land
Policy and Management Act of 1976 (43 U.S.C. 1712, 1713), not later than 90
days after the date on which the Secretary determines that the conditions
described in subsection (b) have been met, and subject to valid existing rights
and applicable law, the Secretary shall convey to the Henderson Redevelopment
Agency all right, title, and interest of the United States in and to the
Federal land.
(b)
Conditions
(1)
Appraisal; fair market
value
(A)
In
general
As consideration for the conveyance under subsection (a),
the Henderson Redevelopment Agency shall pay the fair market value of the
Federal land, if any, as determined under subparagraph (B) and as adjusted
under subparagraph (F).
(B)
Appraisal
The
Secretary shall determine the fair market value of the Federal land based on an
appraisal—
(i) that is conducted in
accordance with nationally recognized appraisal standards, including—
(I) the Uniform Appraisal
Standards for Federal Land Acquisitions; and
(II) the Uniform Standards of
Professional Appraisal Practice; and
(ii) that does not take into
account any existing contamination associated with historical mining on the
Federal land.
(C)
Remediation and
reclamation costs
(i)
In
general
The Secretary shall prepare a reasonable estimate of the
costs to assess, remediate, and reclaim the Three Kids Mine Project
Site.
(ii)
Considerations
The
estimate prepared under clause (i) shall be—
(I) based on the results of a
comprehensive Phase II environmental site assessment of the Three Kids Mine
Project Site prepared by the Henderson Redevelopment Agency or a Responsible
Party that has been approved by the State; and
(II) prepared in accordance
with the current version of the ASTM International Standard E–2137–06 (2011)
entitled Standard Guide for Estimating Monetary Costs and Liabilities
for Environmental Matters.
(iii)
Assessment
requirements
The Phase II environmental site assessment prepared
under clause (ii)(I) shall, without limiting any additional requirements that
may be required by the State, be conducted in accordance with the procedures
of—
(I) the most recent version
of ASTM International Standard E–1527–05 entitled Standard Practice for
Environmental Site Assessments: Phase I Environmental Site Assessment
Process; and
(II) the most recent version
of ASTM International Standard E–1903–11 entitled Standard Guide for
Environmental Site Assessments: Phase II Environmental Site Assessment
Process.
(iv)
Review of certain
information
(I)
In
general
The Secretary shall review and consider cost information
proffered by the Henderson Redevelopment Agency, the Responsible Party, and the
State in the preparation of the estimate under this subparagraph.
(II)
Final
determination
If there is a disagreement among the Secretary,
Henderson Redevelopment Agency, and the State over the reasonable estimate of
costs under this subparagraph, the parties shall jointly select 1 or more
experts to assist the Secretary in making the final estimate of the
costs.
(D)
Deadline
Not
later than 30 days after the date of enactment of this Act, the Secretary shall
begin the appraisal and cost estimates under subparagraphs (B) and (C),
respectively.
(E)
Appraisal
costs
The Henderson Redevelopment Agency or the Responsible Party
shall reimburse the Secretary for the costs incurred in performing the
appraisal under subparagraph (B).
(F)
Adjustment
The
Secretary shall administratively adjust the fair market value of the Federal
land, as determined under subparagraph (B), based on the estimate of
remediation, and reclamation costs, as determined under subparagraph
(C).
(2)
Mine remediation and
reclamation agreement executed
(A)
In
general
The conveyance under subsection (a) shall be contingent
on—
(i) the Secretary receiving
from the State written notification that a mine remediation and reclamation
agreement has been executed in accordance with subparagraph (B); and
(ii) the Secretary
concurring, not later than 30 days after the date of receipt of the written
notification under clause (i), that the requirements under subparagraph (B)
have been met.
(B)
Requirements
The
mine remediation and reclamation agreement required under subparagraph (A)
shall be an enforceable consent order or agreement between the State and the
Responsible Party who will be obligated to perform under the consent order or
agreement administered by the State that—
(i) obligates the Responsible
Party to perform, after the conveyance of the Federal land under this Act, the
remediation and reclamation work at the Three Kids Mine Project Site necessary
to ensure all remedial actions necessary to protect human health and the
environment with respect to any hazardous substances, pollutant, or contaminant
will be taken, in accordance with all Federal, State, and local requirements;
and
(ii) contains provisions
determined to be necessary by the State and the Henderson Redevelopment Agency,
including financial assurance provisions to ensure the completion of the
remedy.
(3)
Notification from
agency
As a condition of the
conveyance under subsection (a), not later than 90 days after the date of
execution of the mine remediation and reclamation agreement required under
paragraph (2), the Secretary shall accept written notification from the
Henderson Redevelopment Agency that the Henderson Redevelopment Agency is
prepared to accept conveyance of the Federal land under subsection (a).
4.
Withdrawal
(a)
In
general
Subject to valid existing rights, for the 10-year period
beginning on the earlier of the date of enactment of this Act or the date of
the conveyance required by this Act, the Federal land is withdrawn from all
forms of—
(1) entry, appropriation,
operation, or disposal under the public land laws;
(2) location, entry, and
patent under the mining laws; and
(3) disposition under the
mineral leasing, mineral materials, and the geothermal leasing laws.
(b)
Existing reclamation
withdrawals
Subject to valid existing rights, any withdrawal
under the public land laws that includes all or any portion of the Federal land
for which the Bureau of Reclamation has determined that the Bureau of
Reclamation has no further need under applicable law is relinquished and
revoked solely to the extent necessary—
(1) to exclude from the
withdrawal the property that is no longer needed; and
(2) to allow for the
immediate conveyance of the Federal land as required under this Act.
(c)
Existing Reclamation
Project and Permitted Facilities
Except as provided in subsection
(a), nothing in this Act diminishes, hinders, or interferes with the exclusive
and perpetual use by the existing rights holders for the operation,
maintenance, and improvement of water conveyance infrastructure and facilities,
including all necessary ingress and egress, situated on the Federal land that
were constructed or permitted by the Bureau of Reclamation before the effective
date of this Act.
5.
ACEC boundary
adjustment
Notwithstanding
section 203 of the Federal Land Policy and Management Act of 1976 (43 U.S.C.
1713), the boundary of the River Mountains Area of Critical Environmental
Concern (NVN 76884) is adjusted to exclude any portion of the Three Kids Mine
Project Site consistent with the map.
6.
Responsibilities of
the parties
(a)
Responsibility of
parties to mine remediation and reclamation agreement
On
completion of the conveyance under section 3, the responsibility for complying
with the mine remediation and reclamation agreement executed under section
3(b)(2) shall apply to the Responsible Party and the State of Nevada.
(b)
Savings
provision
If the conveyance under this Act has occurred, but the
terms of the agreement executed under section 3(b)(2) have not been met,
nothing in this Act—
(1) affects the
responsibility of the Secretary to take any additional response action
necessary to protect public health and the environment from a release or the
threat of a release of a hazardous substance, pollutant, or contaminant;
or
(2) unless otherwise
expressly provided, modifies, limits, or otherwise affects—
(A) the application of, or
obligation to comply with, any law, including any environmental or public
health law; or
(B) the authority of the
United States to enforce compliance with the requirements of any law or the
agreement executed under section 3(b)(2).
7.
Southern Nevada Public
Lands Management Act
Southern
Nevada Public Land Management Act of 1998 (31 U.S.C. 6901 note; Public Law
105–263) shall not apply to land conveyed under this Act.
July 8, 2013
Reported with an amendment, committed to the Committee of
the Whole House on the State of the Union, and ordered to be
printed