AN ACT
To approve the Keystone XL Pipeline.
1.
Keystone XL approval
(a)
In general
TransCanada Keystone Pipeline, L.P. may construct, connect, operate, and maintain the pipeline and
cross-border facilities described in the application filed on May 4, 2012,
by TransCanada Corporation to the Department of State (including any
subsequent revision to the pipeline route within the State of Nebraska
required or authorized by the State of Nebraska).
(b)
Environmental impact statement
The Final Supplemental Environmental Impact Statement issued by the Secretary of State in January
2014, regarding the pipeline referred to in subsection (a), and the
environmental analysis, consultation, and review described in that
document (including appendices) shall be considered to fully satisfy—
(1) all requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and
(2) any other provision of law that requires Federal agency consultation or review (including the
consultation or review required under section 7(a) of the Endangered Species Act of 1973 (16 U.S.C. 1536(a))) with respect to the pipeline and facilities referred to in subsection (a).
(c)
Permits
Any Federal permit or authorization issued before the date of enactment of this Act for the
pipeline and cross-border facilities referred to in subsection (a) shall
remain in effect.
(d)
Federal judicial review
Any legal challenge to a Federal agency action regarding the pipeline and cross-border facilities
described in subsection (a), and the related facilities in the United
States, that are approved by this Act, and any permit, right-of-way, or
other action taken to construct or complete the project pursuant to
Federal law, shall only be subject to judicial review on direct appeal to
the United States Court of Appeals for the District of Columbia Circuit.
(e)
Private property savings clause
Nothing in this Act alters any Federal, State, or local process or condition in effect on the date
of enactment of this Act that is necessary to secure access from an owner
of private property to construct the pipeline and cross-border facilities
described in subsection (a).
Passed the House of Representatives November 14, 2014.Karen L. Haas,Clerk