Library / Laws / 113th / hr / H.R. 2762 / Introduced in House
I
113th CONGRESS
1st Session
H. R. 2762
IN THE HOUSE OF REPRESENTATIVES
July 19, 2013
Mr. Sensenbrenner
introduced the following bill; which was referred to the
Committee on Energy and
Commerce
A BILL
To amend the Federal Power Act to establish a regional
transmission planning process, and for other purposes.
1.
Short title
This Act may be cited as the
Powering America for Tomorrow
Act.
2.
Amendment of the
Federal Power Act
Section 216
of the Federal Power Act (16 U.S.C. 824p) is amended as follows:
(1) By amending the section heading to read as
follows: Regional transmission plans for the interstate
transmission system.
(2) By striking
subsection (i) and redesignating subsections (j) and (k) as subsections (k) and
(l), respectively.
(3) By redesignating
subsections (d) through (h) as subsections (f) through (j),
respectively.
(4) By striking
subsections (a), (b), and (c) and inserting the following:
(a)
Purposes
The
purposes of this section are as follows:
(1) To ensure electric
reliability, fuel diversity, and wholesale power price stability across the
electric transmission grid.
(2) To reinforce,
strengthen, and enhance electric transmission infrastructure as an integrated
network system.
(3) To facilitate the
development of clean energy resources that cannot be located near an existing
transmission facility or load center.
(4) To assist States and electric energy
service providers in meeting the requirements of applicable renewable portfolio
standards.
(5) To take maximum
advantage of smart grid technologies to promote electric grid improvements,
energy efficiency, and demand response.
(6) To coordinate regional planning and local
siting of interstate high-voltage electric transmission systems.
(b)
Definitions
In this section:
(1) The term
bulk-power system has the meaning given such term in section
215(a)(1).
(2) The term
designated region means a region designated under subsection
(c)(1).
(3) The term
Electric Reliability Organization has the meaning given such term
in section 215(a)(2).
(4) The term Interconnection has
the meaning given such term in section 215(a)(5).
(5) The term
regional entity has the meaning given such term in section
215(a)(7).
(6) The term
regional transmission plan means a comprehensive plan required
under subsection (c)(3) for the development of the interstate electric
transmission system in a designated region.
(7) The term
regional transmission planner means a person or entity approved
under subsection (c)(2) to develop and maintain a regional transmission plan
required under this section.
(8) The term regional transmission
project means an overhead or underground transmission facility,
consisting of conductors or cables, towers, manhole duct systems, phase
shifting transformers, reactors, capacitors, substations, and any ancillary
facilities and equipment necessary for the proper operation of the
facility—
(A) that—
(i) operates at or
above a voltage of—
(I) 230 kilovolts
alternating current; or
(II) 300 kilovolts
direct current;
(ii) is a very high
current conductor or superconducting cable that operates at or above a power
equivalent to the power of a conventional transmission cable operating at or
above 230 kilovolts alternating current or 300 kilovolts direct current;
or
(iii) is a renewable
feeder line; and
(B) that is included
in a regional transmission plan submitted to the Commission under subsection
(c)(3).
(9) The term
renewable feeder line means a transmission line that—
(A) operates at or
above a voltage of 100 kilovolts; and
(B) is identified in a regional transmission
plan submitted to the Commission under subsection (c)(3) as a facility that is
to be developed to facilitate collection of electric energy produced by
renewable energy.
(c)
Regional
transmission plans
(1)
Designation of
regions
Not later than 12
months after the date of enactment of this subsection, the Commission, in
consultation with the Electric Reliability Organization, regional entities,
Transmission Organizations, transmission owners, State regulatory authorities
of the States comprising the Eastern Interconnection, and State regulatory
authorities of the States comprising the Western Interconnection, shall
designate one or more regions within the Eastern Interconnection and one or
more regions within the Western Interconnection, to be represented by regional
transmission planners approved under paragraph (2). In determining the
appropriate size and scope of a region, the Commission shall consider the
optimal scope needed to ensure comprehensive regional transmission planning and
operational efficiency, the size and scope of existing Regional Transmission
Organizations and operating bulk-power systems, and methods for interregional
coordination agreements to ensure a sufficiently broad regional transmission
planning process.
(2)
Regional
transmission planners
(A)
Application and
approval
Any person or entity, including a Regional Transmission
Organization or other regionally based planning entity with an established
regional transmission planning process, as determined by the Commission, may
submit an application to the Commission for approval as the regional
transmission planner for a designated region. Not later than 18 months after
the designation of a region under paragraph (1), the Commission shall approve
one such regional transmission planner for each such designated region to
develop and maintain a regional transmission plan required under this
section.
(B)
Consideration
In
approving a regional transmission planner under subparagraph (A), the
Commission shall consider the existing or reasonably anticipated capabilities
of any regionally based planning entity described in such subparagraph in
regional transmission planning.
(C)
Contents of
application
An applicant
entity shall include in an application for approval as the regional
transmission planner for a designated region the operating procedures of such
applicant entity and any method such applicant entity will use to adhere to the
requirements for a regional transmission planning process described in
paragraph (5).
(D)
Compliance
The Commission may review the compliance of
a regional transmission planner approved under subparagraph (A) with the
requirements of this section and any regulations thereunder. If the Commission
finds such a regional transmission planner has failed or is failing to comply
with such requirements or regulations, the Commission may revoke the approval
of such regional transmission planner for a designated region and accept
applications for a new regional transmission planner for such region to be
approved in accordance with this section.
(3)
Regional
transmission plan required
Not later than 2 years after the approval
of a regional transmission planner under paragraph (2), and every 2 years
thereafter, such regional transmission planner shall submit to the Commission
an initial or updated regional transmission plan that meets the requirements of
this section. The Commission shall ensure that each such plan is the result of
a planning process that adhered to the requirements for a regional transmission
planning process described in paragraph (5). The Commission shall make all
regional transmission plans submitted available to the public.
(4)
Regional
transmission plan design
A
regional transmission plan required under this section shall, with respect to a
designated region—
(A) be designed
to—
(i) maintain and
enhance the economic, reliability, and energy security benefits of the regional
electric transmission system, including remediation of electric grid
congestion; and
(ii) anticipate and
facilitate development of electric energy generation from diverse energy
resources; and
(B) consider whether proposals to expand and
upgrade high voltage electric transmission in the designated region and across
the boundaries of the designated region will minimize congestion and promote
service reliability, market integration and efficiency, economic development,
deployment of smart grid technologies, lowest cost delivered electric energy at
wholesale, and the goals of applicable renewable portfolio standards.
(5)
Regional
transmission planning process
The Commission shall ensure each
regional transmission planning process conducted by a regional transmission
planner is consistent with the purposes of this section. The Commission shall
ensure any such planning process—
(A) is
non-discriminatory, independent, and conforms with the planning standards of
Commission Order No. 890 or any successor order;
(B) solicits and
considers the input of local and State policymakers, transmission facility
owners and electric utilities, and market participants;
(C) is sufficiently
broad in geographic and market scope to produce economic and operational
efficiencies;
(D) is designed to
meet the need for the timely construction or modification of regional
transmission projects; and
(E) takes into
account—
(i) all applicable
laws and regulations governing the procurement of electric energy
generation;
(ii) the potential
effect on the future operation of the electric transmission system or on the
regional transmission plan of rejection or withdrawal of a proposed regional
transmission project;
(iii) the development
of transmission facilities for which a completed application for authorization
has been filed and accepted by a State regulatory authority or other applicable
authority before the date of submission of a regional transmission plan under
paragraph (3) but not originating from the planning process;
(iv) the availability of non-transmission
resources such as opportunities for energy efficiency, demand response,
enhancements to economic dispatch, distributed generation, and installation of
new control, metering, or capacity enhancement technologies; and
(v) the development of
the interstate electric transmission system in the designated region for the 10
years after submission of a regional transmission plan under paragraph
(3).
(6)
Transmitting
utilities and Power marketing administrations
Federal power marketing administrations and
transmitting utilities in a designated region shall integrate their
transmission plans with the regional transmission plans required by this
section and shall otherwise participate in a regional transmission planning
process by a regional transmission planner in accordance with this
section.
(7)
Commission
activities
If no regional
transmission planner for a designated region is approved under paragraph (2),
or in the event that an approved regional transmission planner does not timely
submit a regional transmission plan as required under paragraph (3), the
Commission shall designate a planner or undertake the planning activities
described in this subsection for the designated region concerned and develop
such a plan for such designated region expeditiously, in consultation with
State regulatory authorities, as applicable, for all affected States or areas,
the Electric Reliability Organization, regional entities, Transmission
Organizations, and transmission owners within the region, as
appropriate.
(8)
Cost
Allocation
Not later than 18 months after the date of enactment
of this paragraph, the Commission shall, by rule, require that all regional
high voltage electric transmission cost allocation processes and methodologies
adhere to a clear and consistent set of regulatory principles, including, as
appropriate, that the costs of siting and the construction or modification of
transmission facilities shall be allocated consistent with the range and
distribution of benefits within the designated region that are provided by such
facilities, the use of the transmission system, or with other equitable and
economic considerations. In issuing a rule under this paragraph, the Commission
shall consider regional cost allocation processes and methodologies being
developed or in existence as of the date of enactment of this paragraph.
(9)
Plan
coordination
The Commission shall require regional transmission
planners to coordinate planning across regional boundaries within an
Interconnection in order to achieve the purposes of this section.
(d)
Certificate of
public convenience and necessity
(1)
Proposed finding
of public convenience and necessity by regional transmission planner
(A)
Inclusion of
proposed finding in regional transmission plan
As part of a
regional transmission plan submitted to the Commission under subsection (c)(3),
a regional transmission planner may identify a regional transmission project or
projects that such regional transmission planner finds, based on the record of
the regional transmission planning process, is required by, and consistent
with, the public convenience and necessity.
(B)
Public
convenience and necessity certificate request
A regional
transmission planner may submit to the Commission a request to issue a
certificate of public convenience and necessity for a regional transmission
project identified in a regional transmission plan submitted under subsection
(c)(3). Such request shall include a summary of the record developed for such
project during the regional transmission planning process. The request shall be
based on whether such regional transmission project is or will be—
(i) necessary to
ensure regional compliance with reliability standards or remedy violations of
such reliability standards;
(ii) necessary to
provide significant relief from electric transmission congestion as measured by
objective criteria, including consideration of the total cost of congestion,
hours of congestion, and the lack of feasible economic alternative means to
relieve congestion;
(iii) important to the
diversification of energy supply throughout the designated region, including by
meeting the goals of applicable renewable portfolio standards; or
(iv) important to the
development of smart grid technology that is consistent with the policy under
title XIII of the Energy Independence and Security Act of 2007 (42 U.S.C. 17381
et seq.).
(2)
Issuance of
certificate of public convenience and necessity
The Commission may, after notice and
opportunity for hearing, find that a regional transmission project is in the
public convenience and necessity and issue a certificate of public convenience
and necessity for the ownership and operation of such regional transmission
project and the provision of any related services under the jurisdiction of the
Commission if the Commission finds that—
(A) a regional
transmission planner included a proposed finding of public convenience and
necessity for such proposed regional transmission project in one or more
relevant regional transmission plans submitted to the Commission under
subsection (c)(3);
(B) a regional
transmission planner submitted a request for the issuance of such a
certificate;
(C) the proposed
regional transmission project will be used for the transmission of electric
energy in interstate commerce;
(D) the proposed
regional transmission project is consistent with the public interest in terms
of its engineering, reliability, and other economic characteristics and the
purposes of this section; and
(E) the proposed
regional transmission project will maximize, to the extent reasonable and
economical, existing rights-of-way and the transmission capabilities of
existing towers and structures.
(3)
Considerations
In issuing a certificate of public
convenience and necessity under this subsection, the Commission shall give
substantial deference to any proposed finding of public convenience and
necessity by a regional transmission planner in a regional transmission plan
submitted under subsection (c)(3).
(4)
Multiple
projects
The Commission may treat multiple proposed regional
transmission projects in any regional transmission plan as separate for
purposes of determining whether a certificate of public convenience and
necessity should be issued under this subsection.
(5)
Certificate
applications
The Commission shall issue rules specifying—
(A) the form of the
application for a certificate of public convenience and necessity under this
subsection; and
(B) the information to
be contained in such application.
(6)
Environmental
review
(A)
Proposed finding
by regional transmission planner
A proposed finding by a regional
transmission planner of public convenience and necessity regarding a regional
transmission project is excluded from review under the National Environmental
Policy Act of 1969 (42 U.S.C. 4321 et seq.), provided an environmental
assessment or environmental impact statement is required to be prepared by the
Commission under such Act.
(B)
Consideration by
Commission
In determining whether a certificate of public
convenience and necessity should be issued under this subsection, the
Commission may consider, wholly or in part, any draft environmental analysis
conducted by a regional transmission planner or relevant transmission provider
and issued by the regional transmission planner.
(e)
Siting
authority
(1)
Exclusive State
siting authority
A State
shall retain exclusive authority over the siting of any transmission facility
that is not a part of a regional transmission project for which a certificate
of public convenience and necessity has been issued under subsection
(d)(2).
(2)
Federal siting
authority
The Commission may,
after notice and an opportunity for hearing, issue one or more permits for the
construction or modification of a transmission facility if the Commission finds
that—
(A) the transmission
facility was identified as part or all of a regional transmission project for
which a certificate of public convenience and necessity has been issued under
subsection (d)(2);
(B) at least one State
in the designated region for which such regional transmission project is
identified has approved the siting of such transmission facility; and
(C)
(i) a State in which such
transmission facility is to be sited does not have authority to—
(I) approve the siting of the facility;
or
(II) consider the interstate benefits
expected to be achieved by the proposed siting of the transmission facility in
the State;
(ii) the applicant for a permit is a
transmitting utility but does not qualify to apply for a permit for such
transmission facility in a State in which such transmission facility is to be
sited because the applicant does not serve end-use customers in the State;
or
(iii) a State commission or other
entity that has authority to approve the siting of such transmission
facility—
(I) did not issue a decision on an
application seeking approval for the siting of the facility within 1 year after
the date on which the applicant submitted a completed application to the State
commission or other authority;
(II) denied a complete application seeking
approval for the siting of the transmission facility without proposing an
alternate site; or
(III) authorized the siting of the facility
subject to conditions that unreasonably interfere with the siting of the
transmission
facility.
.
(5) In subsection (f),
as redesignated by paragraph (3), by striking subsection (b) and
inserting subsection (e).
(6) In subsection (g),
as redesignated by paragraph (3), by striking subsection (b) and
inserting subsection (e).
(7) In subsection (h),
as redesignated by paragraph (3), by striking subsection (e) and
inserting subsection (g).
(8) In subsection (k)(2), as redesignated by
paragraph (2), by striking Subsection (h)(6) and inserting
Subsection (j)(6).
(9) By amending
subsection (l), as redesignated by paragraph (2), to read as follows:
(l)
Applicability
This
section applies only to States located in the Western Interconnection and
States located in the Eastern Interconnection and does not apply to the States
of Alaska or Hawaii, or to areas under the authority of the Electric
Reliability Council of
Texas.
.