Library / Laws / 113th / hr / H.R. 1948 / Introduced in House
I
113th CONGRESS
1st Session
H. R. 1948
IN THE HOUSE OF REPRESENTATIVES
May 13, 2013
Mr. Mica (for
himself, Mr. Rahall, and
Mr. Gibbs) introduced the following
bill; which was referred to the Committee
on Transportation and Infrastructure
A BILL
To amend the Federal Water Pollution Control Act to
preserve the authority of each State to make determinations relating to the
State’s water quality standards, and for other purposes.
1.
Short title
This Act may be cited as the
Clean Water Cooperative Federalism Act
of 2013.
2.
State water
quality standards
(a)
State water
quality standards
Section
303(c)(4) of the Federal Water Pollution Control Act (33 U.S.C. 1313(c)(4)) is
amended—
(1) by redesignating
subparagraphs (A) and (B) as clauses (i) and (ii), respectively;
(2) by striking
(4) and inserting (4)(A);
(3) by striking
The Administrator shall promulgate and inserting the
following:
(B) The Administrator shall
promulgate
;
and
(4) by adding at the
end the following:
(C) Notwithstanding subparagraph (A)(ii), the
Administrator may not promulgate a revised or new standard for a pollutant in
any case in which the State has submitted to the Administrator and the
Administrator has approved a water quality standard for that pollutant, unless
the State concurs with the Administrator’s determination that the revised or
new standard is necessary to meet the requirements of this
Act.
.
(b)
Federal licenses
and permits
Section 401(a) of such Act (33 U.S.C. 1341(a)) is
amended by adding at the end the following:
(7) With respect to any discharge, if a
State or interstate agency having jurisdiction over the navigable waters at the
point where the discharge originates or will originate determines under
paragraph (1) that the discharge will comply with the applicable provisions of
sections 301, 302, 303, 306, and 307, the Administrator may not take any action
to supersede the
determination.
.
(c)
State NPDES
permit programs
Section 402(c) of such Act (42 U.S.C. 1342(c)) is
amended by adding at the end the following:
(5)
Limitation on
authority of Administrator to withdraw approval of State
programs
The Administrator may not withdraw approval of a State
program under paragraph (3) or (4), or limit Federal financial assistance for
the State program, on the basis that the Administrator disagrees with the State
regarding—
(A) the implementation
of any water quality standard that has been adopted by the State and approved
by the Administrator under section 303(c); or
(B) the implementation
of any Federal guidance that directs the interpretation of the State’s water
quality
standards.
.
(d)
Limitation on
authority of Administrator To object to individual
permits
Section 402(d) of such Act (33 U.S.C. 1342(d)) is amended
by adding at the end the following:
(5) The Administrator may not object
under paragraph (2) to the issuance of a permit by a State on the basis
of—
(A) the Administrator’s interpretation of
a water quality standard that has been adopted by the State and approved by the
Administrator under section 303(c); or
(B) the implementation of any Federal
guidance that directs the interpretation of the State’s water quality
standards.
.
3.
Permits for
dredged or fill material
(a)
Authority of EPA
Administrator
Section 404(c) of the Federal Water Pollution
Control Act (33 U.S.C. 1344(c)) is amended—
(1) by striking (c) and
inserting (c)(1); and
(2) by adding at the
end the following:
(2) Paragraph (1) shall not apply to any permit
if the State in which the discharge originates or will originate does not
concur with the Administrator’s determination that the discharge will result in
an unacceptable adverse effect as described in paragraph
(1).
.
(b)
State permit
programs
The first sentence of section 404(g)(1) of such Act (33
U.S.C. 1344(g)(1)) is amended by striking The Governor of any State
desiring to administer its own individual and general permit program for the
discharge and inserting The Governor of any State desiring to
administer its own individual and general permit program for some or all of the
discharges.
4.
Deadlines for
agency comments
Section 404 of
the Federal Water Pollution Control Act (33 U.S.C. 1344) is amended—
(1) in subsection (m)
by striking ninetieth day and inserting 30th day (or the
60th day if additional time is requested); and
(2) in subsection
(q)—
(A) by striking
(q) and inserting (q)(1); and
(B) by adding at the
end the following:
(2) The Administrator and the head of a
department or agency referred to in paragraph (1) shall each submit any
comments with respect to an application for a permit under subsection (a) or
(e) not later than the 30th day (or the 60th day if additional time is
requested) after the date of receipt of an application for a permit under that
subsection.
.
5.
Applicability of
amendments
The amendments made
by this Act shall apply to actions taken on or after the date of enactment of
this Act, including actions taken with respect to permit applications that are
pending or revised or new standards that are being promulgated as of such date
of enactment.
6.
Impacts of EPA
regulatory activity on employment and economic activity
(a)
Analysis of
impacts of actions on employment and economic activity
(1)
Analysis
Before taking a covered action, the
Administrator shall analyze the impact, disaggregated by State, of the covered
action on employment levels and economic activity, including estimated job
losses and decreased economic activity.
(2)
Economic
models
(A)
In
general
In carrying out paragraph (1), the Administrator shall
utilize the best available economic models.
(B)
Annual GAO
report
Not later than December 31st of each year, the Comptroller
General of the United States shall submit to Congress a report on the economic
models used by the Administrator to carry out this subsection.
(3)
Availability of
information
With respect to any covered action, the Administrator
shall—
(A) post the analysis
under paragraph (1) as a link on the main page of the public Internet Web site
of the Environmental Protection Agency; and
(B) request that the Governor of any State
experiencing more than a de minimis negative impact post such analysis in the
Capitol of such State.
(b)
Public
hearings
(1)
In
general
If the Administrator
concludes under subsection (a)(1) that a covered action will have more than a
de minimis negative impact on employment levels or economic activity in a
State, the Administrator shall hold a public hearing in each such State at
least 30 days prior to the effective date of the covered action.
(2)
Time, location,
and selection
A public hearing required under paragraph (1) shall
be held at a convenient time and location for impacted residents. In selecting
a location for such a public hearing, the Administrator shall give priority to
locations in the State that will experience the greatest number of job
losses.
(c)
Notification
If the Administrator concludes under
subsection (a)(1) that a covered action will have more than a de minimis
negative impact on employment levels or economic activity in any State, the
Administrator shall give notice of such impact to the State’s Congressional
delegation, Governor, and Legislature at least 45 days before the effective
date of the covered action.
(d)
Definitions
In
this section, the following definitions apply:
(1)
Administrator
The term Administrator means
the Administrator of the Environmental Protection Agency.
(2)
Covered
action
The term covered action means any of the
following actions taken by the Administrator under the Federal Water Pollution
Control Act (33 U.S.C. 1201 et seq.):
(A) Issuing a regulation, policy statement,
guidance, response to a petition, or other requirement.
(B) Implementing a new or substantially altered
program.
(3)
More than a de
minimis negative impact
The term more than a de minimis
negative impact means the following:
(A) With respect to
employment levels, a loss of more than 100 jobs. Any offsetting job gains that
result from the hypothetical creation of new jobs through new technologies or
government employment may not be used in the job loss calculation.
(B) With respect to
economic activity, a decrease in economic activity of more than $1,000,000 over
any calendar year. Any offsetting economic activity that results from the
hypothetical creation of new economic activity through new technologies or
government employment may not be used in the economic activity
calculation.