,,american ,,society ,,of ,,civil ,,engineers ,,instituted #aheb ,,transactions ,paper ,no4 #aaeb ,,the ,,new ,,york ,,tunnel ,,extension ,,of ,,the ,,pennsylvania ,,railroad4 ,,the ,,east ,,river ,,division4 ,,by ,,alfred ,,noble1 ,,past-,,president1 ,,am4 ,,soc4 ,c4 ,e4 ,a general outline of the work included in this ,division has been given by ,general ,c4 ,w4 ,raymond1 ,m4 ,am4 ,soc4 ,c4 ,e41 in the first paper of the series4 ,the few pages following are intended only as a note to connect his paper with the more detailed descriptions of the execution of the work1 which will be supplied by the ,resident ,engineers in immediate charge4 ,soon after the ,company's project was made public1 in the latter part of #aija1 borings were begun in the ,east ,river1 and a few weeks later in ,manhattan and ,long ,island ,city4 ,a preliminary base line was measured on the ,manhattan side1 and temporary transit stations were established on buildings from which all borings in the river were located4 ,the river borings were all wash-borings made from a pile-driver boat4 ,after the results were plotted on the map1 contour lines were drawn to indicate the rock surface1 and profiles along the tunnel lines were plotted from the contours2 as the borings were preliminary to the final location of the tunnels1 and in many cases at some distance from the tunnel lines1 considerable divergence from the actual rock surface was expected1 and realized in a few places1 yet on the whole the agreement was very good4 ,the borings revealed two depressions or channels where the rock surface passed below the grade of the projected tunnels1 these depressions being separated by a rock reef which extends down stream from ,blackwell's ,island4 ,in #cb;d and #cc;d ,streets in ,manhattan1 borings were made from the river to the station site at intervals of about #ajj ft41 wash-borings and core-borings alternating4 ,in ,long ,island ,city1 where the tunnel lines were to pass diagonally under the passenger station building and passenger yard of the ,long ,island ,railroad and under streets and private property1 the arrangement of borings was less regular1 although the alternation of wash-borings and core-borings was carried out as far as practicable4 ,after the final location of the work1 additional borings were made1 particularly on shaft sites and also along the approaches and in the ,sunnyside ,yard1 ,long ,island ,city4 ,a triangulation was carried across the river with a measured base on each side4 ,it was impossible to measure directly between the extremities of either base4 ,the bases were measured with #ajj-;ft4 steel tapes1 supported every #bj ft41 stretched with a uniform pull1 and frequently compared with standardized tapes4 ,on account of the crowded condition of the streets during the hours of daylight and evening1 most of the work was done between #aj ,p4 ,m4 and #e ,a4 ,m4 ,similar measurements were made in the streets along the tunnel lines4 ,angle readings were repeated many times1 as is usual in such work4 ,fig4 #a shows the triangulation1 the street measurements being omitted4 ,levels were first transmitted across the river by simultaneous observations of the river surface2 then by several repetitions1 across ,blackwell's ,island and the narrow channels on each side1 where the longest sights were about #aajj ft42 and1 finally1 by several lines through the tunnel of the ,east ,river ,gas ,company at #gast ,street4 ,the franchise granted by the ,city of ,new ,york provided for the sale to the ,railroad ,company of the portions of #cb;d ,street between ,seventh and ,eighth ,avenues1 and between ,eighth and ,ninth ,avenues4 ,later1 the ,company acquired by purchase the portion of #cb;d ,street between ,ninth and ,tenth ,avenues4 ,the franchise granted sub-surface rights under streets around the station site to within #ai ft4 of the street surface under ,seventh1 ,eighth1 and ,ninth ,avenues2 to within #cj in4 of the street surface under #cast and #cc;d ,streets1 except that1 under the sidewalks opposite the station1 that is to say1 the south sidewalk in #cast ,street and the north sidewalk in #cc;d ,street1 the construction must be at least #e ft4 below the street surface4 ,in carrying out the work1 full use of these rights was made under ,eighth ,avenue1 but only under such portions of ,seventh and ,ninth ,avenues as were indispensable for access by trains to the station area4 ,it was not practicable to make full use of the rights granted under #cast and #cc;d ,streets without incurring great expense for supporting adjacent buildings or for injuries to them1 and1 after careful consideration1 the arrangement shown in the plans was decided on1 making about #de of the sub-surface area under these streets available at track level4 ,illustration3 ,,fig4 #a4--,triangulation ,system ,east ,river ,tunnel ,the work of the ,east ,river ,division at this site embraced the excavation to the depth necessary for railroad tracks1 and the building of a retaining wall extending in #cast ,street from the east side of ,ninth ,avenue to the west side of ,seventh ,avenue1 thence northward along ,seventh ,avenue for a distance of #aee4e ft42 also a retaining wall in #cc;d ,street from the west side of ,seventh ,avenue to the east side of ,ninth ,avenue1 and thence southward along ,ninth ,avenue for a distance of #acf4c ft4 ,this work was placed under contract ,june #bast1 #aijd1 with the ,new ,york ,contracting and ,trucking ,company1 and later assigned by that company to the ,new ,york ,contracting ,company-,pennsylvania ,terminal1 and was carried out under the direction of ,george ,c4 ,clarke1 ,m4 ,am4 ,soc4 ,c4 ,e41 as ,resident ,engineer1 by whom it will be described in detail4 ,illustration3 ,,plate ,,ix4--,map of ,portion of ,manhattan ,island from #bc;d to #djth ,streets1 ,showing ,former ,topography ,from ,map ,made by ,gen4 ,egbert ,l4 ,viele in #ahfe ,the station tracks leading eastward from the station will converge under ,seventh ,avenue and for some distance farther east1 and pass into two three-track tunnels1 one under #cb;d ,street and the other under #cc;d ,street1 at the respective distances of #aib and #djb ft4 from ,seventh ,avenue4 ,a typical cross-section of the three-track tunnel is shown on ,plate ,,xii4 ,the converging sections were considered as easterly extensions of the station1 and were not included in the ,east ,river ,division4 ,within a few hundred feet 7,plate ,,xiv71 the tracks are reduced to two1 each passing into a single tube1 the two tunnels under each street being formed in one excavation1 the distance between center lines of tunnels being #bj ft4 #d in4 ,this construction has been termed a twin tunnel1 and a typical cross-section is shown on ,plate ,,xii4 ,the tunnels continue on tangents under the streets to ,second ,avenue where they curve to the left by #a #cj' curves1 passing under private property1 gradually diverging and passing through shafts just east of ,first ,avenue4 ,about #cej ft4 west of the shaft1 the divergence of the two lines from each street becomes sufficient to leave a rock dividing wall between them1 and thence eastward each tunnel is formed in a separate excavation4 ,a typical cross-section of the two separated tunnels is shown on ,plate ,,xii4 ,it thus appears that eastward from the station the lines constitute a four-track railroad1 each track being in a separate tunnel2 for convenience of the work these lines were designated ,a1 ,b1 ,c1 and ,d1 from north to south4 ,illustration3 ,,plate ,x4--,manhattan ,shaft1 ,lines ,a and ,b ,at an early date1 when the organization of the engineering staff was taken up1 ,charles ,l4 ,harrison1 ,m4 ,am4 ,soc4 ,c4 ,e41 was appointed ,principal ,assistant ,engineer4 ,he was directly in charge of all parts of the work1 and all ,resident ,engineers reported to him4 ,george ,leighton1 ,m4 ,am4 ,soc4 ,c4 ,e41 was placed in charge as ,resident ,engineer of the #cc;d ,street lines from the west end of the three-track tunnel to the shaft and also eastward from the shaft under ,east ,river4 ,as he was not then able to endure the effects of compressed air1 the work under the river was transferred to ,james ,h4 ,brace1 ,m4 ,am4 ,soc4 ,c4 ,e41 as ,resident ,engineer4 ,before the completion of the land tunnels under #cc;d ,street1 ,mr4 ,leighton accepted more responsible employment elsewhere1 and ,mr4 ,brace assumed charge of them also4 ,francis ,mason1 ,m4 ,am4 ,soc4 ,c4 ,e41 was in charge as ,resident ,engineer of the #cb;d ,street lines during their entire construction1 and also of the tunnels extending these lines eastward from the ,first ,avenue shaft under the river4 ,the work just described as the #cb;d and #cc;d ,street lines1 terminating at the easterly end at the ,first ,avenue shafts1 was placed under contract on ,may #bith1 #aije1 with the ,united ,engineering and ,contracting ,company4 ,the plans then provided for three-track tunnels from the west end of the work under the contract eastward #a1fbh ft4 in #cb;d ,street and #a1dah ft4 in #cc;d ,street to the west line of ,fifth ,avenue1 with a descending grade of #j4d2 this was to constitute1 in a degree1 an extension of the station1 where trains could stand without brakes while awaiting signals to proceed to or from the station4 ,from ,fifth ,avenue eastward to the lowest point under the river1 the grade was to be #a4e on all lines4 ,later1 during construction1 when excavating westward under #cc;d ,street from ,fifth ,avenue1 the surface of the rock was broken through1 disclosing quicksand2 within the next few days trial drill holes through the tunnel roof at #cb;d ,street and ,fifth ,avenue showed a thin cover with quicksand above it4 ,the conditions had been indicated in a general way by borings made before construction was begun1 but they proved to be rather worse than anticipated4 ,on the topographical map of ,manhattan ,island1 made by ,general ,egbert ,l4 ,viele in #ahfe1 is shown a watercourse which had its source near what is now ,broadway and #ddth ,street1 flowing thence along the west side and south end of ,murray ,hill1 passing under the present site of the ,waldorf-,astoria ,hotel1 crossing #cc;d ,street at the point where the rock surface was broken through in the tunnel excavation1 as above stated1 crossing #cb;d ,street at its intersection with ,fifth ,avenue1 where trial drilling showed thin rock cover over the tunnel excavation1 passing thence eastward a short distance south of #cb;d ,street1 which it recrossed near ,third ,avenue1 and finally discharging into the ,east ,river near #cdth ,street1 and a little west of the present ,first ,avenue4 ,the ancient creek apparently followed the course of a valley in the rock1 the valley having become filled to a considerable depth with very fine quicksand4 ,this concurrence of depressions in the rock surface with the watercourse shown on ,viele's map was noted in so many places and the difficulties of construction were so serious at these places1 that a section of the map showing the old topography along and adjacent to the station and tunnel lines is reproduced in ,plate ,,ix4 ,illustration3 ,,plate ,,xi4--,long ,island ,shaft4 ,lines ,a and ,b ,the unfavorable conditions developed at ,fifth ,avenue affected both the construction of the tunnels and the maintenance of adjacent buildings4 ,it would be necessary to construct the tunnels in open cut for a large part of the way westward1 causing serious inconvenience to the public2 the buildings were mostly of the older class1 founded in earth1 but there were several modern high buildings with foundations in the same material2 some of these had been built since the tunnels were planned4 ,in view of these added risks and the increased cost of construction1 the value of the three-track construction was reconsidered1 and two important changes were made in the plans4 ,the first of these was to continue the twin tunnel westward to ,sixth ,avenue in #cb;d ,street1 and to a point #ahj ft4 west of ,sixth ,avenue in #cc;d ,street2 the twin tunnel being #i-a_/b ft4 less in height than the three-track tunnel and #i ft4 narrower1 the change reduced the difficulties considerably4 ,where the three-track tunnel was thus eliminated1 there was no longer objection to a steeper grade1 so that1 going eastward from the station1 a grade of #j4h in #cc;d ,street and #j4i in #cb;d ,street was substituted for the original #j4d grade4 ,from the west line of ,fifth ,avenue eastward short sections with descending grades of #j4c connect with the original #a4e grade near ,madison ,avenue4 ,the effect of these two changes--type of tunnel and grade--was to lower the roof of the tunnels at ,fifth ,avenue about #ae ft41 which made it practicable to avoid open cutting east of ,sixth ,avenue4 ,a full account of the construction of the cross-town tunnels will be given by the ,resident ,engineers4 ,permanent shafts were made on both sides of the ,east ,river1 those in ,manhattan being located a few feet east of ,first ,avenue1 and those in ,long ,island ,city being located1 one in the so-called ,annex ,slip1 the other in the pier just south of it4 ,the two railroad lines coming from #cb;d ,street in ,manhattan1 and curving to the left at ,second ,avenue1 are about #cd ft4 apart between centers at ,first ,avenue1 and it was convenient to make the shaft large enough to cover both lines4 ,borings had shown that the excavation for the tunnels would break out of the rock about #bjj ft4 east of ,first ,avenue4 ,it was desirable to carry the tunnel excavation eastward from the shaft in normal air far enough to permit of building at least #ej ft4 of tunnel and installing air-locks1 so that compressed air might be available when the rock surface was broken through4 ,the location adopted1 and shown on ,plate ,,xiii1 had the further advantages that the rock surface was several feet above the level of the top of the tunnels1 and access to the river for receiving and discharging materials could be had without crossing any street4 ,similar reasons governed the location of the north shaft for the lines from #cc;d ,street4 ,on the ,long ,island side of the river there were only two feasible locations meeting these conditions1 particularly in respect to a safe thickness of rock above the tunnels1 one near the pierhead line1 the other just outside the bulkhead line1 and for many minor reasons the latter was preferable4 ,the center lines of each pair of tunnels were #cg ft4 apart1 and each shaft1 therefore1 was made to cross both lines of a pair1 the same as on ,manhattan side of the river4 ,it was not expected1 however1 that the ,long ,island shafts could be built conveniently or the tunnels begun from them in normal air4 ,the decision to make the shafts of permanent construction was based not only on the desirability of having access to and egress from the tunnels near the banks of the river for convenience of the workmen or exit for passengers in case of accident1 but to facilitate ventilation2 these locations divide the entire lengths of tunnels east of the station into three parts1 two of which were approximately #d1jjj ft4 each1 and the other about #e1ejj ft4 ,the accident risk was believed to be very small1 while much weight was given to the feature of facilitating ventilation4 ,further studies have enhanced the importance attached to ventilation1 and it is now intended to provide appliances for mechanical ventilation at all shafts4 ,the plans of the shafts are shown on ,plates ,x and ,,xi4 ,the caissons for the shafts are of structural steel1 with double walls1 filled between with concrete1 including a cross-wall between and parallel to the tunnels4 ,all these structures were fitted for sinking with compressed air1 if that should prove necessary4 ,although borings had shown that rock would be found at all the shaft sites several feet above the tunnel level1 it could not be determined in advance of excavation whether the caissons would have to be sunk to full depth2 if sound1 unfissured rock were found1 the sinking could be stopped above the tunnel level2 but1 if not1 the caissons1 in any case1 would have to be sunk far enough to permit placing a water-tight floor below the tunnels1 and the tunnels themselves begun through openings in the side-walls of the caisson2 such openings1 therefore1 closed by removable bulkheads1 were provided in all caissons4 ,illustration3 ,,plate ,,xii4--,typical ,tunnel ,sections ,as already stated1 the grade of #a4e from ,fifth ,avenue eastward was fixed with reference to the lowest point of the river bed in order to give the requisite cover over the tunnels at the deepest point of the channel on the west side of the reef1 where the river bottom was about #fj ft4 below mean high tide for a short distance4 ,on the other hand1 as the use of compressed air in building the tunnels was anticipated1 an excessive depth below the water surface was to be avoided as far as possible2 it was necessary1 however1 to continue the descending grade some further distance until the tunnels were mostly in rock1 so that drainage sumps under the tunnels could be made readily4 ,eastward from the sumps the tunnels had a rising grade of #j4g to the established bulkhead line on the ,long ,island side1 giving a cover at the points where the tunnels enter rock1 a short distance westward1 of about #aj ft4 7if the dredging plane should be fixed at some future time at #dj ft4 below mean low tide1 as may be reasonably anticipated74 ,eastward from the bulkhead line1 ,tunnels ,a1 ,b1 and ,d have ascending grades of about #a4be1 while ,tunnel ,c rises at the rate of #a4i in order to effect a crossing over ,tunnel ,b west of the portals4 ,this feature was introduced in order to place the two west-bound tracks together through the ,sunnyside ,yard1 and the heavier grade1 being downward with the traffic1 was not objectionable4 ,the arrangement of grades and tracks in the approaches and in ,sunnyside ,yard would require the introduction of too much detail to be taken up here1 but will be dealt with in the paper on the ,sunnyside ,yard4 ,it was recognized from the inception of the project that the tunnels under the ,east ,river would be the most difficult and expensive section of the ,east ,river ,division4 ,the borings had shown a great variety of materials to be passed through1 embracing quicksand1 coarse sand1 gravel1 boulders1 and bed-rock1 as well as some clayey materials4 7,see ,plate ,,xiii47 ,the rock was usually covered by a few feet of sand1 gravel1 and boulders intermixed1 but1 in some places1 where the rock surface was at some distance below the tunnel grade1 the material met in tunneling was all quicksand2 the nearest parallels in work previously done were some of the tunnels under the ,thames1 particularly the ,blackwall tunnel1 where open gravel was passed through4 ,before the plans for the ,east ,river tunnels were completed1 work had been resumed1 after many years' interruption1 in the old ,hudson ,river tunnels between #aeth ,street1 ,jersey ,city1 and ,morton ,street1 ,manhattan1 and sand materials were passed through for a short distance4 ,these experiences satisfied nearly all the engineers in any way connected with the work that the shield method was the most suitable for the ,east ,river tunnels1 and the plans for the work were based on its adoption4 7,see ,plate ,,xii for cross-sections1 etc47 ,other methods1 as stated by ,general ,raymond in the introductory paper1 were advocated1 particularly caisson constructions and the freezing process1 the latter being urged very strongly1 and1 when proposals were invited1 in ,october1 #aijc1 bidders were informed that alternative methods would be taken into consideration4 ,bids were received and opened on ,december #aeth1 #aijc4 ,only one bidder proposed to carry out the work on the basis of unit prices1 but the prices were so low that the acceptance of the proposal was deemed inadmissible2 no bid based on caisson methods was received2 several offers were made to perform the work by the shield method1 in accordance with the plans1 for a percentage of its cost1 and one was submitted1 on a similar basis1 covering the use of the freezing method4 ,the firm of ,s4 ,pearson and ,son1 ,limited1 of ,london1 ,england1 submitted a proposal for building the tunnels by the shield method1 on a modification of the percentage basis1 and as this firm had built the ,blackwall tunnel within the estimates of cost and was the only bidder having such an experience and record in work in any way similar to the ,east ,river tunnels1 negotiations were continued between that firm and the railroad company4 ,the original plans and specifications contemplated that all tunnels between the ,first ,avenue shafts in ,manhattan and ,east ,avenue in ,long ,island ,city would be shield-driven1 and that work would proceed simultaneously eastward from the ,first ,avenue shafts and both eastward and westward from the ,long ,island ,city shafts located west of ,front ,street at the river1 requiring twelve shields4 ,when making their proposal1 ,s4 ,pearson and ,son1 ,limited1 suggested that shields might be started from the east end of the work and arrive at the ,front ,street shafts as soon as these shafts could be completed1 and proposed sinking a temporary shaft transversely across all four lines near the east end of the work just west of ,east ,avenue1 from which1 within a short time1 to drive toward ,front ,street by the use of shields4 ,the railroad company accepted the suggestion for the additional shaft1 although the greater part of the tunnels east of ,front ,street was built without shields4 ,after several months of negotiation1 a contract was entered into on ,july #gth1 #aijd1 with ,s4 ,pearson and ,son1 ,incorporated1 a corporation of the ,state of ,new ,york organized by the ,english firm for the purpose of entering into and carrying out this contract4 ,the main features had been agreed upon1 and work had begun about two months before4 ,the contract embraced the permanent shafts in ,manhattan and ,long ,island ,city1 the tunnels between these shafts1 and their extension eastward in ,long ,island ,city to ,east ,avenue1 including in all about #bc1fjj ft4 of single-track tunnels4 ,the contract had novel features1 and seemed to be peculiarly suitable for the unknown risks and the unusual magnitude of the work4 ,a fixed amount was named as contractor's profit4 ,if the actual cost of the work when completed1 including this sum named as contractor's profit1 should be less than a certain estimated amount named in the contract1 the contractor should have one-half of the saving4 ,if1 on the other hand1 the actual cost of the completed work1 including the fixed sum for contractor's profit1 should exceed the estimated cost named in the contract1 the contractor should pay one-half the excess and the railroad company the other half2 the contractor's liability was limited1 however1 to the amount named for profit plus #a1jjj1jjj2 or1 in other words1 his maximum money loss would be #a1jjj1jjj4 ,any further excess of cost was to be borne wholly by the railroad company4 ,the management of the work1 with some unimportant restrictions1 was placed with the contractor2 the relations of the engineer1 as to plans1 inspection1 etc41 were the same as in ordinary work1 and the interest of the contractor to reduce cost was the same in kind as in ordinary work4 ,illustration3 ,,plate ,,xiii4--,plan and ,profile4 ,east ,river ,tunnels ,on account of the extent of the work embraced in this contract1 and the dangerous exposure to compressed air required in most of it1 it was divided into three residencies2 two of these1 including also the cross-town tunnels1 have been described2 the third1 with ,s4 ,h4 ,woodard1 ,m4 ,am4 ,soc4 ,c4 ,e41 as ,resident ,engineer1 embraced all tunnels from the easterly end of the work near ,east ,avenue in ,long ,island ,city to the meeting points under the river and also the permanent shafts in ,long ,island ,city4 ,a few months after the execution of the principal contract1 the work to be done was extended eastward #ajg4e ft41 across ,east ,avenue4 ,the extensions of the tunnels were built without cast-iron linings and with an interior cross-section of the same height as the tube tunnels1 but somewhat narrower4 ,the work was also extended westward from the ,first ,avenue shafts to include the excavation of top headings in each tunnel for a distance of #ajj ft4 and an enlargement to full size for #ej ft4 ,the borings having shown that soft earth existed below the grade of the tops of the tunnel under the passenger station building of the ,long ,island ,railroad on the east side of ,front ,street1 and that earth of varying character would be met in places beyond the station building under the railroad tracks in the passenger yard and the street car tracks in ,borden ,avenue1 it had been decided1 before proposals were invited1 to extend the metal lining eastward to ,east ,avenue1 at the east end of the work embraced in the original contract1 where the rising tunnel grades approached the surface of the ground so closely that their further extension would be in open cut4 ,in places where the tunnels were wholly in rock1 the weight of the cast-iron tunnel lining was reduced #dc2 where the surface of the rock was below the top of the tunnel1 but above the axis1 the reduction of weight was somewhat less1 about #be2 notwithstanding these savings1 the cost of the tunnels was probably increased by the use of the cast-iron lining2 on the other hand1 when passing through bad ground1 a section of tunnel could be made absolutely safe more quickly by erecting the lining as soon as a length of a few feet of tunnel was ready2 under a crowded passenger yard1 this feature had great value4 ,the execution of the work under this contract will be described fully by the ,resident ,engineers4 ,the plant assembled by the contractors is believed to be the most extensive ever placed on a single piece of work1 and will be described in detail by their ,managing ,engineer1 ,henry ,japp1 ,m4 ,am4 ,soc4 ,c4 ,e4 ,for convenience in receiving materials to be used in construction1 and to facilitate the disposal of excavated materials1 one pier was leased on the east side of the ,hudson ,river1 two on the west side of the ,east ,river and three on the east side4 ,excavated materials from the station1 the cross-town tunnels1 and the river tunnels1 were placed on barges furnished by ,mr4 ,henry ,steers under several contracts embracing also the disposal of the materials4 ,in the earlier part of the work1 they were used as fill in the freight terminal of the ,pennsylvania ,railroad at ,greenville on the west side of the ,upper ,bay2 when the fill at this place was completed1 the materials were sent to the tunnel company's yard on the ,passaic1 at ,harrison1 ,n4 ,j41 and a small part to the embankment in the ,meadows ,division4 ,on account of the occasional closing of the ,passaic by ice1 this involved the possibility of1 and to some extent resulted in1 interruptions to the work of excavation4 ,the contract for the cross-town tunnels carried an option in favor of the company to require the contractor for those tunnels to dispose of materials at a stated price1 and in the latter part of #aijg1 when the excavation in these tunnels was being pushed rapidly1 the railroad company1 unwilling to incur the responsibility for delays during the winter1 availed itself of this option4 ,the disposal of materials was an important part of the work1 and will be dealt with more fully by the ,resident ,engineers4 ,illustration3 ,,plate ,,xiv4--,map and ,profile1 ,cross-,town ,tunnels ,at the time the contract was made with ,s4 ,pearson and ,son1 ,incorporated1 it had not been determined whether mechanical ventilation would be provided for the tunnels1 and therefore the contract with that firm did not include the final concrete lining at the shafts1 above the inverts of the tunnels4 ,after the adoption of plans for mechanical ventilation1 in the latter part of #aijh1 the plans for lining the shafts with concrete1 including flues for conducting air to the tunnels1 and stairways for ingress and egress1 were completed1 and the work was placed under contract2 it will be described in detail by ,f4 ,m4 ,green1 ,assoc4 ,m4 ,am4 ,soc4 ,c4 ,e4 ,at the east end of the work under the ,pearson contract1 the rising grade of the tunnels brought them so near the surface of the ground that their extension eastward could be carried out more readily in open cut than by tunneling4 ,the locations of the portals could be varied somewhat1 and they were built on rock which was found in rather narrow ridges at convenient places4 ,tunnels ,b and ,d have a common portal2 ,tunnels ,a and ,c have separate ones1 the portal for ,tunnel ,c being located about #hjj ft1 west of the others as a result of its crossing over ,tunnel ,b1 as already explained4 ,eastward from the portals1 the track system expands1 in order to provide connections with the tracks of the ,long ,island ,railroad to and from ,long ,island ,city1 with the ,new ,york ,connecting ,railroad and ,new ,england lines1 and with the storage and cleaning yard known as the ,sunnyside ,yard extending to the west side of ,woodside ,avenue1 #b-c_/d miles east of the ,east ,river4 7,plate ,,xv47 ,the yard and approaches are designed to avoid grade crossings by opposing trains4 ,the various general features of the yard and tunnel approaches1 bridge crossings1 and street closings1 have been described in sufficient detail by ,general ,raymond in the introductory paper4 ,illustration3 ,,plate ,,xv4--,plan and ,profile of ,lines ,a and ,b1 and ,sunnyside ,yards ,for convenience in placing the work under contract1 a line was drawn #aj ft4 west of ,thomson ,avenue1 dividing the work east of that embraced in the ,pearson contract into two parts4 ,the work west of the line was placed under the immediate direction of ,george ,c4 ,clarke1 ,m4 ,am4 ,soc4 ,c4 ,e41 as ,resident ,engineer1 with ,naughton ,company and ,arthur ,mc,mullen1 ,contractors2 ,mr4 ,louis ,h4 ,barker was ,resident ,engineer of the part east of the dividing line1 with the ,degnon ,realty and ,terminal ,improvement ,company as the principal contractors4 ,the substructures of the several bridges in or across the yard were included in these contracts1 but the superstructures were carried out by various bridge companies1 and other minor features were executed by other contractors4 ,more complete descriptions of the plans and of the execution of the work will be given by the ,resident ,engineers4